Construction of CCHP Power Plant

Start date of the project

1395

Project description

‌The combined cooling, heating and power systems (CCHP) have many advantages including high efficiency, high reliability, low fuel consumption, and short construction time. Saba Power and Energy Group has planned for construction of a 10 MW CCHP as its medium-term plan for 2016-2019. The first phase of the 3 MW combined cooling, heating and power systems (CCHP) has already begun in the location of the Mostazafan Foundation.

Title phase 1 phase 2
Titlephase onephase two
Unit Number and Capacity (MW)
Status of the projectDoing
Approval date95/10/06
Last situationAbout 30% of physical progress
Year of construction
Run year