The 4 MW Hootan Small-Scale Power Plant is located in Hootan village, Maraveh Tappeh county, Golestan province. This power plant was commissioned in 2024, leveraging the capabilities of domestic knowledge-based companies for design and construction using fully Iranian gas-fired generators. In addition to resolving voltage drops for over 5,000 regular subscribers, this facility covers 2 major subscribers, comprising 14 villages and 7 border checkpoints.
| Title | phase 1 | phase 2 | phase 3 |
|---|---|---|---|
| Title | phase one | phase two | phase three |
| Unit Number and Capacity (MW) | 1*4 | ||
| Status of the project | In operation | ||
| Approval date | 2023 | ||
| Last situation | In operation | ||
| Year of construction | 2024 | ||
| Run year | 2024 |